Summary
The county is weighing design options for the Canyon Median, landscaping many residents drive past daily. Superintendent Wendy Parker presented options but no decision was made yet.
At a glance
- Total mentions
- 4
- Last 30 days
- 2
Discussed at 2 meetings in the last 60 days; most recently Oct 27, 2026.
Impact analysis
Total construction cost isn't known yet; about $38,000 spent on design so far.
Residents and commuters who use the canyon corridor would see improved landscaping.
Cyclists worry curb lips and vegetation could push cars into bike lanes; some residents oppose any spraying.
Mentions & discussions (4)
County Council - Regular Session — October 27, 2026
The county showed a combined conceptual design for the Canyon Road medians — stamped concrete, colored gravel and low-water plantings costing about $546,115 — aiming to cut maintenance and keep workers safe. Councilors were split and asked for more safety and cost data before approval.
Parks and Recreation Board — October 8, 2026
The Canyon Road medians get a design refresh based on community survey results. The Parks Board backed the plan unanimously; now County Council decides whether to approve it.
Transportation Board — September 3, 2026
Two stamped-concrete design concepts are being voted on by public survey through September 13. No new irrigation is planned and median footprints won't change; board members raised cyclist and deflection safety concerns.
Parks and Recreation Board — August 13, 2026
The county is weighing design options for the Canyon Median, landscaping many residents drive past daily. Superintendent Wendy Parker presented options but no decision was made yet.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Los Alamos County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.