Summary

The arena's old grandstand and pavilion were torn down after a safety study found them unsafe and the site non-ADA compliant. The council approved $2.87 million total to rebuild with a new elevated grandstand, pavilion, ADA restrooms, parking and chip-seal sidewalks, with substantial completion by July 2027.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Feb 10, 2026.

Impact analysis

💰Financial impact

Total project budget is $2.87 million including a 15% contingency; savings revert to the CIP fund.

✅Who benefits

Rodeo and equestrian users, spectators including people with disabilities, and the broader community using the arena.

⚠️Who could be affected

Arena users face closures during construction; user groups noted restrooms close about five months a year and some earlier input was initially ignored.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Los Alamos County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.